MES, a manufacturing execution system, looks like a command centre in vendors’ presentations: screens full of KPIs, schedules, tracking of every single part. A small or medium-sized manufacturer with twenty machines and a planner with a spreadsheet needs only a small part of that, and in a different order from the one the price list suggests. Below: which features solve real shop-floor problems and which can be postponed.
What problems MES is supposed to solve
Before anyone names a system, name the problem. Four keep recurring in small and medium-sized companies:
- We don’t know what is happening on the shop floor right now. We know the status of a work order from the end-of-shift report, retyped in the morning.
- We don’t know why the machine stood idle. Downtime is recorded in a notebook or nowhere.
- We don’t know how much was really produced and how much went to scrap. The quantities in the reports don’t match the warehouse.
- The operator does not have what they need to hand: the drawing, the instructions, the checklist, information about a change in the work order.
Each of them has a solution smaller than “MES”. Only all of them together add up to a system.
Features that solve these problems
- Machine reporting at the moment of the event. A panel at the workstation (tablet, terminal, button): work order start, good parts, scrap, stop with a reason. This is the core; without it the rest has no data.
- Downtime log with the cause. A list of causes agreed with the shop floor (breakdown, no material, changeover, no operator), selected with one tap, not typed in.
- Live work order status. For the planner and the supervisor: which work order is on which machine, how much is done, when it will finish at the current pace.
- Documentation at the workstation. The current drawing, instructions, parameters; the version from the system, not from a drawer.
- Data transfer to the ERP. The closed work order, consumption and finished goods reach the ERP without retyping.
Features worth postponing
- Detailed scheduling with optimisation. It requires reliable operation times, which a company without production reporting does not have. First a year of collecting actual times, then the algorithm.
- Tracking every single part (genealogy). Needed in regulated industries; elsewhere, batch level is enough.
- KPIs on screens across the shop floor. As long as the data is incomplete, the KPI shows the incompleteness, not efficiency.
- Integration with the controllers of all machines. Good for machines that report on their own; for the rest, a button and a panel give the same result more cheaply. Connecting old machines is a separate project.
- Quality, maintenance and tool room modules in one package. Each of them is a separate process with a separate owner; rolled out together, none of them gets rolled out at all.
How to start
With production reporting, not licences. One line, a panel at each workstation, three events: start, quantity, stop with a reason. After a month, the company has its first actual times and causes of downtime. That is the moment to talk about what is needed next.
A list of causes from the shop floor, not from the textbook. Operators select a cause if the list is theirs. Twenty items from the vendor’s manual will end with everyone choosing “other”.
A panel that does not get in the way. A report should take seconds. If the operator has to log in with a password and go through three screens, they will start reporting at the end of the shift, just as before.
The shift supervisor as owner. The shop-floor data is theirs; they check whether the reports are complete, and they are the first to use the downtime report.
What to calculate
The time between an event on the shop floor and its entry in the system (today: end of shift plus retyping in the morning). The number of work orders closed in the ERP with different quantities from those on the shop floor. Weekly downtime with no known cause, if anyone records it at all. These are the “before” measures a company can collect in a week from notebooks and spreadsheets.
Checklist
- Named problems, not a system name.
- First scope: production reporting and downtime on one line.
- List of downtime causes agreed with the operators.
- Panel at the workstation with a report taking a few seconds.
- Connection to the ERP for closed work orders.
- Decision on scheduling and KPIs only after actual times have been collected.
At ErgoFlow, we build the reporting layer as panels at the machines and a shop-floor application tailored to the line, with transfer to the ERP, and we extend it with further features only when the data justifies it. A description is on the Automation page, and examples of shop-floor applications on the Applications page.
This article is for information only. The scope of the first stage, the number of workstations and the way of connecting to the ERP depend on the company; we set them after an audit.